|
 |
|
 |
Welcome to Siemens – Highlights &
Innovations in Transmission and Distribution |
|
 |
Printer friendly
version >> please,
click here |
International Workshop
for
800kV High Voltage Direct Current (HVDC) Systems
at the 25th – 26th Feb, 2005 in New Delhi
/ India
hosted by POWERGRID, India and EPRI, USA
1. Plans for use of HVDC voltage
higher than 600 kV
The growth and extension of power grids and consequently the
introduction of high voltage levels have
been driven by a big growth of power demand over decades. In the next
20 years, power consumption
in developing and emerging countries is expected to increase for 220
%.
|
|
Priorities in future developments will be given to
low costs at still adequate technical quality and reliability. The use
of HVDC technology is the solution, especially for bulk power
transmission from the remote generating stations over long distances
to load centers (ref. Fig.1). In the future it will be necessary to
transmit bulk power > 4000 MW over more than 2000 km. Therefore it is
important to develop HVDC transmission technologies for voltage levels
above 600 kV.
In countries like Brazil, China, India, South
Africa and Russia a number of large capacity hydro-electric projects
are being developed with load centers located at distant locations.
China is planning to cover 26 % of their power demand by hydropower
and 60 % by coal-fired power plays in 2020. Unfortunately the
distribution of China’s power energy resources and consumption center
are extremely unbalanced. Now China will choose
|

Fig.1: Costs
of Transmission Systems
AC in comparison with DC
Ref. to Furnas, Brazil: “New
HVDC Projects Under Study in Brazil and Some
Experience in ± 800 kV HVDC”
|
|
long distance and
large capacity transmission from west to east as well as north to
south as strategic plan. 2005 to 2010 is an important period for
launching Ultra High Voltage (UHV) projects in China. For example for
an
±800kV
UHVDC for long distance with large transportation capacity (5400
-6200MW).
The Government of India has
taken initiative for harnessing over 50,000 MW power potential in
different river basins in the country. POWERGRID has been entrusted
with the task of planning and implementing power transmission systems
to link generation and load centers. The total power transfer capacity
of about 12,000 MW would be required by the year 2016-17 and the
length of the transmission lines involved would be in the order of
2000-2500 km. A proposed solution maybe an UHVDC with a bipole rating
of 6000MW, 800kV (2000 km) from the pooling station in NE region to
Agra. The realization in two steps: First stage to build a 12-p 600kV
valve group (VG) and in the second stage to add a 12-p 200kV VG in
series is one realistic option.
In South Africa the WESTCOR JV Project (3500MW-4500MW over ?
km) is another example for planed UHVDCs at 800kV. As well as the
HVDC 750kV Transmission Ekibastuz – Centre (6000MW, 2400 km) in
Russia which was unfortunately stopped during the dissolution of the
USSR. Even in Brazil several new UHVDC projects are under study.
2. 800 kV HVDC Converter
configuration, Insulation coordination, Test
voltage levels
and Conditions
All these study cases from countries like Brazil, Russia and South
Africa show that HVDC transmission at 800kV is feasible and doable,
but there are several challenges which have to be considered.
The 800kV HVDC transmission system includes the HVDC transmission line
with different requirements for insulation, clearances and corona
performance. There is evidence to suggest that several transmission
line design companies have and can design an 800kV transmission line.
The converter station is also part of a HVDC. Its design and
construction at 800kV is impacted by the |
following
equipment and factors:
-
Converter
transformers,
-
External
insulation,
- HVDC
thyristor valves
(valve hall refer to Fig.2)
-
External Measuring Devices
Especially the external
insulation causes a big challenge. Pollution (particularly urban, by
automobiles and industrial as well as salted air, and to a lesser
extent by agriculture) affects the steady state and switching surge
withstands levels. Under DC voltage insulators electro-statically
collect airborne particles so much so that often the flashover level
outdoor insulation under DC is lower than under AC voltages. |
|

Fig.2: HVDC Valve hall |
|
External insulation performance
The performance of external insulation in HVDC converter stations
is recognized to be the critical factor in determining the reliability
of the transmission. Of all the different types of insulators used in
a converter station wall bushings especially prone to flashover. Many
of the flashovers on the wall bushings have occurred in conditions
during which flashovers would not have been anticipated on the basis
of contamination level or the degree of wetting that can cause a
flashover.
Other insulators than wall bushings such as transformer bushings,
reactor bushings, measuring devices housings and to a much lesser
degree post insulators have been also experienced flashovers.
The answer maybe the reduction of the number of
wall bushings and/or applying adequate surface material with
hydrophobic properties. Another opportunity is the use of indoor DC
switchyards and the insert of composite bushings and insulators.
Higher creepage distances and longer insulators increase the
performance of external insulation; therefore new machines for
production may be required.
Not only in terms
of pollution, but also the large size of insulators represent another
challenge for internal stresses and long life
especially for bushings. Further development work is needed on
internal stresses and relationship between internal and external
stresses.
|
|
Converter Transformer
One of the most critical components in an HVDC station is the
converter transformer. Especially the insulation barrier around
the oil end of the valve winding bushing is the critical area of the
converter transformer. Its failure in general will mean DC power
failure. The future UHVDC projects can not afford to have such
failures. At 800kV DC proper design
review of this area is recommended. Transport limits and converter
configurations determine type and size. Investments in testing
facilities are needed.
Testing
The report from EPRI and Cigré 14-32 recommend test levels for
800kV systems which have to be carefully reviewed and considered. The
high test levels as well as the larger size of 800 kV equipments are a
big challenge for the test availability of testing facilities.
A
Siemens 397 MVA / 1 phase / 3 winding converter transformer is shown
in Fig. 3.
|

Fig. 3: Siemens Testing
Facility for
Converter Transformers
|
|
3. Readiness
for 800 kV HVDC equipment – Manufacturer’s View & Conditions
From the
Siemens point of view UHVDC system at 750-800kV is technically
feasible. Almost all DC
equipments like
transformers, smoothing reactors, wall bushings, arresters,
disconnectors refer to Siemens Power Transmission and Distribution “UHVDC
System and Equipment” and are within
Siemens product scope. Existing and proven technology can be fully
utilized for design, manufacturing and testing of UHVDC equipment. R&D
is only needed in the area of valve side bushings and in specific
testing facilities. Some design verification shall be made to cover
the requirements on creepage distance and mechanical strength of
porcelain. Good experience from existing DC systems and modern
MO-Arresters allow reasonably reduction of insulation levels from
former suggestions.
A coordinating R&D
program in few key areas will ensure that the availability of design
of the UHVDC equipment for the first application is expected to be
within 12 months.
The stage wise
development of the UHVDC systems offer the benefits of the gradually
increase of power demand, the adding of new power generations in steps
and therefore an optimized time period of investments.
In the planning stage the reservation of space for expansion in
the station layout as well as the final current, voltage rating and
the OHL design have to be considered. The choice of a
particular configuration will depend on:
-
Economics,
-
Reliability and availability,
-
Size and weight of the
converter transformers and restrictions for transport
A flexible control and protection
concept is necessary.
Siemens is the pioneer in designing and delivering
HVDC Equipment for the world’s first HVDC system at voltage above
500kV (ref. Fig.4).
|

Fig. 4: Cahora Bassa, Mozambique -
South Africa
|
|
Our presentation “6000MW
UHVDC System and Stage Implementation” at
the workshop in India shows an example for the stage wise development
of the UHVDC system. Series converter groups, parallel converter
groups and separate dipole schemes are feasible options for evacuation
of large power over long distance. Final selection shall base on
overall evaluation taking line length, power rating and time period
between stages into account.
4.
Concluding
Session & Conditions
The
development of the 800kV HVDC (UHVDC) does not represent an
unreasonable risk. The UHVDC transmission line is the feasible and
economical answer for bulk power transmission over long distances to
cover the extremely increase of an energy demand in countries like
India and China. Nevertheless challenges for external insulation,
testing facilities and testing levels, the relationship between
internal and external stresses at bushings and the size of the
converter transformers have to be managed. For transformer, basic work
is needed in understanding short term and long term effects of DC
stress and use of appropriated insulation grading and barriers. A
coordinating R&D program in few key areas will ensure that the
availability of design of the UHVDC equipment for the first
application is expected to be within the near future. |
|