|
 |
|
 |
Welcome to
Siemens – Highlights & Innovations in Transmission and Distribution |
|
 |
Printer friendly
version >> please,
click here |
|
|
|

Gas-Insulated Transmission Line (GIL)
Today and Tomorrow
1. Today’s Use of GIL
The
GIL is transmission technology is based on the technology developed
for Gas-Insulated Switchgear (GIS) more than 35 years ago. In
substations beside the purpose of breaking, switching, disconnecting
and grounding also transmission of electrical energy gas insulated
technology is used. In transmission cases GIL is applied for example
to connect a GIS with the high voltage power transformers, which are
usually placed in a distance of 10 – 20 meters and sometimes 300 – 400
meters away from the switchgear. In cases of GIS connected to the
overhead line where the distances between the phases are much wider in
GIS. Another field of GIL application is cross connections inside of
substations, where directly buried GILs or GILs laid in concrete
trenches are used instead of overhead lines.
In
many cases GILs are laid in a tunnel in cases of cavern power plants.
In 1974 the world wide first the GIL was build at the hydro power
plant Schluchsee in Germany, shown in Figure 1.

Figure 1: GIL installed at the Hydro Power Plant at Schluchsee,
Germany
1
600 MVA
Transformer
Rated Voltage 420
kV
2
Encapsulated Surge
Arrestors
Rated Impulse Withstand Voltage
1640
kV
3
Transfer Switching
units
Rated Current
2000 A
4
GIL
Connection Rated
Short-Time Current
53
kA
5
Open Air Surge Arrestor
6
Overheadline
|
This GIL
is still in operation without any problems. The GIL connects the high
voltage power transformer (1) placed inside the cavern in the mountain with
the overhead line (6) outside the mountain. At the top
entrance open air surge arrestors (5) and in the cavern encapsulated surge
arrestors (5) are protecting the GIL against overvoltages. A transfer switch
(3) allows the connection of the 600 MVA power transformer to the GIL in the
tunnel (4). Such applications are typical for GIL, and have been applied
world wide in a total length of more then 200 kms. Reliability by this GIL
has been proven high in more than 35 years of operation under all kind of
environmental conditions. GIL may be layed directly in the ground covered
with soil, installed in tunnels or in concrete trenches or ducts or above
ground by using steel structures.
2.
Tomorrow Use of GIL
The use of
GIL tomorrow and in the near future will be guided by the needs of long
distance power transmission applications incases where overhead lines can
not be used and high power ratings are needed. This may be the situation in
cities and large metropolitan areas, or if landscape protection reasons are
given, or in conjunction with traffic tunnels. In a more far future also
DC-GIL may be used for very long transmission lines to connect new remote
generation areas with the load centers.
2.1
Long Distance AC-GIL
The needs
of the future electric power transmission is influenced by the concentration
and increase of power supply in cities and metropolitan areas, the use of
new renewable energy sources (wind farms) and the improvement (or retention)
of the supply reliability in a deregulated electricity market.
A few
examples shall be given:
·
TransEuropean Networks
In Europe
the cross national border electric power transmission is limiting the
electric power trade. Traditionally the cross border links are only built to
act as a emergency supply in cases of supply problems in the neighbor
country. Today the cross border links are needed to allow electricity trade
and to bring competition to the energy market. Therefore the European
Community has drawn a priority list of cross border transmission links to
improve the situation. The GIL will play an important role in cases where
overhead lines can not be built and cables are not practical because of the
transmission length and/or the transmitted power.
|
·
Offshore Windfarms
New
offshore windfarms are planned in many locations in the world,
generating high amounts of electrical energy offshore, mean out of
sight from the coast. This is usually the case in areas where the
electrical load is low, so that new transmission lines to the load
centers are needed. In Germany for example the offshore windfarms are
planned to be in the North Sea and the load centers are in the west,
middle and south with distances of 300 km to 600 km. The low public
acceptance level of overhead lines may lead to problems in getting the
right of way to build an overhead line, and it may leave the GIL as
the underground solution available to transmit high amounts of energy
over long distances at the maximum economical and ecological
acceptance.
·
Improved Reliability of Electric Power
Supply of Cities
The
world-wide concentration of electrical load in cities and metropolitan
areas needs for the future new strong high voltage connections right
into the centre of the load. At 400 kV or 500 kV rated voltages and
with currents of 2500 A up to 3150 A the GIL offers the possibility to
make electrical energy available in the needed quantity and quality of
the load centre in the city or metropolitan area.
Two
principle laying methods may be used for such long distance GIL: the
directly buried version, where the GIL is laid similar to gas pipe
lines, and the laying in a tunnel, which can be a tunnel only for
electricity or together with street or railroad tunnels.
2.2
Long Distance DC-GIL
In
a more far future the long distance DC-GIL might be used for
underground transmission lines. Using the advantages of the high
reliability of gas insulated systems and the much lower cost of steel
pipes.
Some pre development works and first applications in DC-GIS have
shown that DC-GIL is feasible, and might have the following basic
design data:
The
main insulating gas is Nitrogen (N2) with a low (10 - 20 %)
of Sulphurhexaflourid (SF6). Such gas mixture can insulate
the DC high voltage reliable for a long time. Such gas mixtures are
used in low temperature applications for high voltage circuit breakers
mainly in the arctic regions since more than 30 years. The advantage
of using a DC-GIL is, that the enclosure pipe can be manufactured by
steel pipes, because the DC current does not induce eddy currents in
the enclosure. This reduces the cost coopared to AC-GIL where aluminum
is used for the enclosure.
|
 |
DC-GIL does not have capacitive loads so
that
very long distances may be installed. The
laying
of the DC-GIL will be the same way as AC and
looks for directly
buried version as shown in
Figure 2 and for the tunnel laid version as
shown
in Figure 3 |
|
 |
|
Fig.
2: Directly buried version of GIL |
Fig.
3: Tunnel laid GIL as operation at the Geneva Airport since 2000.
|
|
3.
Conclusion
Gas
insulated transmission lines (GIL) have show their high reliability in
more then 200 km of GIL in operation world wide, and over more then 30
years of successful use. The future requirements on the transmission
network are increasing power transmission rating, economical and
ecological acceptance, low transmission losses, high safety, high
reliability and easy to install and operate systems. GIL offers all
these features and will be used in future also for long distance
applications.
|
|